Building a House in Nigeria from Overseas: Complete 2025 Guide

Build your Nigerian home from UK, US, or Canada without losing money. Complete guide: costs, timelines, remote monitoring, contractor management, and how to avoid the 7 costly mistakes.
You're 6,000 miles away. Your contractor just sent another text: "We need more money for cement." You've already sent $45,000. The house should be roofed by now. Instead, you're looking at photos of a foundation that doesn't look much different from last month.
Your cousin (who was supposed to "oversee things") hasn't been to the site in three weeks. Your contractor's phone is off. Your money is in Nigeria. You're in London, New York, or Toronto. And you're asking yourself the question every diaspora Nigerian building from overseas asks:
"Did I just make the biggest mistake of my life?"
Here's the truth: Building a house in Nigeria from overseas is absolutely possible. Hundreds of diaspora Nigerians do it successfully every year. But it requires a completely different approach than building if you lived there.
I've managed 200+ overseas building projects. Some finished on time and under budget. Others turned into money pits and heartbreak. The difference? The system you set up BEFORE you send the first dollar.
This is that system. Everything you need to build your Nigerian home from overseas without losing money, your mind, or both.
Why Most Overseas Building Projects Fail (And How Yours Won't)
Let's start with brutal honesty. 40% of diaspora building projects either:
- Never finish
- Cost 2-3x the original budget
- Take 2-3x longer than planned
- End up in family disputes
- Require complete demolition and rebuild
Here are the four failure patterns:
Failure Pattern #1: The Trust Trap (35% of failures)
What happens:
- You send money to family member/"trusted" friend
- They "manage" the project
- Progress is slow, excuses are many
- More money keeps disappearing
- When you finally visit, the work done doesn't match the money spent
Real example: David (Toronto) sent $80,000 to his brother to build a 4-bedroom house. After 2 years, he visited to find only a foundation. His brother had used the money for personal expenses, always planning to "replace it later."
The fix: Never mix family and money. Professional project manager from day one.
Failure Pattern #2: The Contractor Con (30% of failures)
What happens:
- Contractor gives low quote to win job
- Collects 50% upfront (standard practice)
- Uses your money on other projects
- Claims materials cost more than expected
- Work stops unless you send more money
- Threatens to walk away if you complain
Real example: Sarah (London) paid contractor ₦25M ($16,700) upfront. Six months later, work was 20% done. Contractor said cement prices doubled. She paid another ₦15M. Two months later, same story. Total spent: ₦47M. Real work done: Worth ₦22M.
The fix: Milestone-based payments. Quantity surveyor verification. No payment without proof of work.
Failure Pattern #3: The "We Do Things Differently Here" Disaster (20% of failures)
What happens:
- You want things done to standard
- Contractor says "We don't do it that way in Nigeria"
- You're not there to argue
- They do it their way (the cheap/wrong way)
- House has serious structural issues
- Expensive to fix or impossible
Real example: Michael (New York) specified waterproofing for bathroom floors. Contractor said "Not necessary in Nigeria, we use tiles." Michael insisted via text, contractor said "Okay." Visit revealed no waterproofing. Bathroom leaked through ceiling below. Cost to fix: Demolish entire bathroom and rebuild.
The fix: Detailed specifications. Site supervision with photos. Third-party inspections at key stages.
Failure Pattern #4: The Scope Creep Money Pit (15% of failures)
What happens:
- Original plan: 4-bedroom bungalow
- Foundation started
- "Let's add a floor" (family pressure)
- "Let's make it 5 bedrooms"
- "Let's add a boys quarters"
- Budget doubles
- Project stalls
- Never finishes
Real example: Ngozi (Canada) budgeted $100,000 for a 4-bed bungalow. Father suggested adding a floor "since we're building anyway." Mother wanted guest room. Brother needed boys quarters. Final cost: $240,000. Took 4 years instead of 18 months.
The fix: Lock the plan. No changes after foundation. Ever.
Now, here's how to avoid all four...
The Complete Remote Building System (18-Month Timeline)
This is the exact process that results in finished houses, happy owners, and budgets that don't explode.
PHASE 1: Pre-Construction (Months 1-3)
Month 1: Planning & Design
Week 1-2: Land Verification
Before building anything, confirm your land is actually yours:
✅ Land registry verification ($500-1,000)
- Confirm title is genuine
- No pending disputes
- Boundaries are clear
- You can legally build there
✅ Survey and soil test ($800-1,500)
- Professional land surveyor
- Soil bearing capacity test (determines foundation type)
- Site analysis report
Critical: If soil test shows poor bearing capacity, foundation costs increase 30-50%. Know this BEFORE budgeting.
Week 3-4: Architectural Design
Hire architect (budget: $3,000-$8,000 depending on size):
What you get:
- Detailed architectural drawings
- Floor plans
- Elevations
- Sections
- 3D renderings
- Bill of Quantities (BOQ)
Must-haves in your contract with architect:
- Unlimited revisions until you approve
- Designs include plumbing/electrical layouts
- They oversee first site visit
- They verify contractor's initial measurements
Red flag: Architect who says "just send rough idea, we'll figure it out." No. You approve EVERY detail before construction starts.
Month 2: Approvals & Budgeting
Week 1-2: Building Approvals
Submit plans to local government (varies by location):
| Location | Approval Cost | Timeline | Notes |
|---|---|---|---|
| Lagos | $1,500-3,000 | 4-8 weeks | Strict enforcement |
| Abuja | $1,200-2,500 | 6-10 weeks | Bureaucratic |
| Other states | $800-1,500 | 4-12 weeks | Less strict |
Do NOT skip this. Building without approval = government can stop project or demolish completed building.
Week 3-4: Detailed Budget
Hire Quantity Surveyor ($1,500-3,000) to create detailed cost breakdown:
Sample 4-Bedroom House Budget (Lagos, 2025):
| Item | Cost (₦) | Cost ($) | % of Total |
|---|---|---|---|
| Foundation | ₦8,000,000 | $5,330 | 10% |
| Block work | ₦12,000,000 | $8,000 | 15% |
| Roofing | ₦10,000,000 | $6,670 | 12.5% |
| Windows/Doors | ₦6,000,000 | $4,000 | 7.5% |
| Electrical | ₦5,000,000 | $3,330 | 6% |
| Plumbing | ₦4,000,000 | $2,670 | 5% |
| Tiling | ₦8,000,000 | $5,330 | 10% |
| Plastering/Painting | ₦6,000,000 | $4,000 | 7.5% |
| Kitchen/Bath fittings | ₦7,000,000 | $4,670 | 9% |
| POP/Ceiling | ₦4,000,000 | $2,670 | 5% |
| Contingency (15%) | ₦10,500,000 | $7,000 | 13% |
| TOTAL | ₦80,500,000 | $53,670 | 100% |
Add to this:
- Project manager: $8,000-12,000 (whole project)
- Generator/Solar: $6,000-12,000
- Perimeter fence: $5,000-10,000
- Borehole: $3,000-5,000
- Gate: $2,000-4,000
Real total for move-in ready: $77,670-96,670
Rule: Whatever your quantity surveyor quotes, add 20% buffer. Things WILL cost more.
Month 3: Team Assembly
Your Core Team (Non-negotiable):
1. Project Manager ($8K-12K for whole project)
Their job:
- Daily site presence
- Verify all material deliveries
- Manage contractor
- Send daily photos/weekly videos
- Approve milestone payments
- Resolve issues immediately
How to find them:
- Construction management firms
- Recommended by architect
- Professional property management companies
- Never: Family members (unless they're professional project managers and you pay them)
Contract must include:
- Daily site reports
- Photo documentation
- Material tracking sheets
- Budget variance reports
- Penalty for project delays
- Payment tied to completion milestones
2. Contractor ($0 upfront - paid for work done)
How to select:
- Interview 5-6 contractors
- Request 3 previous project references
- Visit their completed projects IN PERSON (or have PM do it)
- Check their projects 1-2 years after completion (quality appears over time)
- Verify they have insurance
Red flags:
- "Pay me 50% upfront"
- "I can start immediately" (Good contractors are booked 2-3 months ahead)
- No insurance
- Can't provide verifiable references
- Dramatically cheaper than others (20%+ below market = corner cutting)
3. Quantity Surveyor ($1.5K-3K)
Their job:
- Verify material quantities
- Check work quality at each stage
- Approve contractor payments
- Prevent over-billing
Critical: QS reports to YOU, not contractor. Pay them directly.
PHASE 2: Foundation & Structure (Months 4-9)
Months 4-5: Foundation
Timeline: 6-8 weeks
Cost: ~10% of total budget
Payment: 25% on excavation, 75% on completion
Your PM should send:
- Week 1: Excavation photos (depth, dimensions)
- Week 2: Reinforcement steel photos (check diameter, spacing)
- Week 3: Concrete pouring video (watch for water ratio)
- Week 4: Foundation curing photos
- Week 5-6: Damp-proof course photos
Critical inspection points:
✅ Foundation depth matches soil test recommendation
- Good soil: 900mm-1200mm depth
- Poor soil: 1500mm-2000mm depth
- If contractor says "we don't need to go that deep," fire them
✅ Reinforcement steel is correct gauge
- Foundation: 16mm-20mm diameter bars
- If they use 12mm "to save money" = future cracks guaranteed
✅ Concrete ratio
- Should be 1:2:4 (cement:sand:granite)
- Watch pouring video for consistency
- Watery concrete = weak foundation
Cost control:
- Pre-approve cement supplier with your PM
- All steel should be weighed on delivery
- PM takes photos of every delivery truck
DO NOT PAY until QS confirms foundation is complete and correct.
Months 6-8: Block Work & Roofing
Timeline: 10-14 weeks
Cost: ~27.5% of total budget
Payment: 30% at lintel level, 40% at roof level, 30% on completion
Block work (Months 6-7):
Your PM sends weekly:
- Block count per delivery
- Mortar mix verification
- Wall alignment photos
- Lintel steel reinforcement
What to watch for:
❌ Using substandard blocks
- Good blocks: 450mm x 225mm x 225mm, machine-made
- Bad blocks: Hand-molded, uneven sizes
- Test: Ask PM to pour water on block. If it absorbs water fast = poor quality
❌ Weak mortar mix
- Should be 1:5 (cement:sand)
- Contractor might use 1:7 or 1:8 "to save money"
- Result: Walls crack within years
Roofing (Month 8):
Critical decisions (Make BEFORE construction starts):
| Roofing Type | Cost/sqm | Lifespan | Pros | Cons |
|---|---|---|---|---|
| Aluminum sheets | ₦8,000-12,000 ($5-8) | 15-20 years | Affordable, easy | Noisy in rain, heats up |
| Stone-coated tiles | ₦15,000-20,000 ($10-13) | 30-50 years | Attractive, durable | More expensive |
| Concrete tiles | ₦12,000-18,000 ($8-12) | 40+ years | Very durable, cool | Heavy (stronger structure needed) |
Roofing inspection checklist:
✅ Roof trusses are treated wood (termite protection)
✅ Spacing matches architectural plan
✅ Roofing sheets overlap correctly
✅ Ceiling boards are waterproof-treated
✅ Ventilation included (prevents heat buildup)
Month 8 is your STOP point: After roofing, you should visit the site (or send trusted representative) for first major inspection.
What to check:
- Doors and windows placement correct?
- Room sizes match plans?
- Foundation showing any cracks?
- Walls vertical and aligned?
- Roof waterproof?
If anything is wrong, fix it NOW. Cheaper to demolish a wall now than to live with a mistake forever.
PHASE 3: Finishing (Months 10-15)
Months 10-11: Electrical & Plumbing
Timeline: 8 weeks
Cost: ~11% of total budget
Payment: 30% on rough-in, 40% on testing, 30% on final connection
Electrical rough-in:
Must-haves (specify in writing):
- Separate circuits for AC units
- Generator changeover switch
- Solar-ready wiring
- Surge protectors on main panel
- Proper earthing system
Your PM verifies:
- Wire gauge matches electrical load
- Conduits (not surface wiring)
- Socket placement matches your plan
- Main panel properly labeled
Plumbing rough-in:
Must-haves:
- PVC pipes (not PEX unless high-quality)
- Isolation valves for every fixture
- Wastewater pipes properly sloped
- Hot water system installed correctly
Common contractor shortcuts:
❌ Using smaller pipe diameter "to save money"
❌ No vents on wastewater pipes (causes gurgling, slow drains)
❌ Wrong trap types (smells leak into house)
Insist on pressure testing:
- Water system pressurized for 24 hours
- Any leaks fixed before walls close
- PM videos this test
Months 12-13: Plastering, Tiling, POP
Timeline: 8 weeks
Cost: ~22.5% of total budget
Payment: 25% on plastering, 25% on tiling, 25% on POP, 25% on completion
Plastering:
Quality check:
- Walls smooth and vertical (use spirit level)
- No hollow sounds when tapped
- Edges and corners sharp
- Thickness consistent (15mm-20mm)
Tiling:
Decisions to make NOW (while still overseas):
| Area | Tile Type | Cost/sqm | Notes |
|---|---|---|---|
| Living areas | Porcelain/Ceramic | ₦5,000-12,000 ($3-8) | Choose exact brand/color |
| Bathrooms | Non-slip ceramic | ₦4,000-8,000 ($2.7-5) | Waterproof grout essential |
| Kitchen | Porcelain | ₦6,000-15,000 ($4-10) | Easy to clean |
| Bedrooms | Tiles or wood | ₦8,000-25,000 ($5-17) | Wood = more expensive |
Critical: Buy ALL tiles at once. Same batch. Different batches = slightly different colors.
PM sends:
- Tile layout plan before installation
- Daily installation photos
- Grouting color confirmation
POP (Plaster of Paris) ceiling:
Popular in Nigeria, but requires skill:
✅ Hire POP specialist (not general contractor)
✅ Designs should be approved by you (photos/drawings)
✅ PM verifies ceiling is level before POP
✅ No POP in bathrooms/kitchen (moisture damage)
Months 14-15: Painting & Fixtures
Timeline: 6-8 weeks
Cost: ~16.5% of total budget
Payment: 30% on undercoat, 40% on finish, 30% on fixtures
Painting:
Colors: Choose with your architect. Get paint codes. Specify brand.
Process must be:
- Surface preparation (filling, sanding)
- Primer coat
- 2-3 finish coats
- Exterior: Weather-resistant paint
Contractor shortcuts:
- Skipping primer
- Only 1 finish coat
- Mixing cheap paint "to save money"
Fixtures (Kitchen, Bathrooms, Doors, Windows):
Option 1: You buy and ship (from UK/US)
- Pros: Higher quality, you choose exactly
- Cons: Shipping costs, customs hassle
- When: High-end fixtures, specific brands
Option 2: Buy in Nigeria
- Pros: Easier, no shipping
- Cons: Limited choices, quality varies
- When: Standard fixtures, budget builds
Must specify:
- Brand and model number of every fixture
- Kitchen cabinets: Custom-built on site (provide drawings)
- Doors: Specify solid wood or hollow core
- Windows: Aluminum or UPVC (UPVC better for security)
PHASE 4: Finishing Touches & Handover (Months 16-18)
Month 16: External Works
Perimeter fence: $5,000-10,000
- Block wall: 6ft minimum height
- Metal gate: Heavy-duty with locks
- Consider electric gate if budget allows
Compound finishing:
- Paving or interlocking stones
- Drainage channels
- Gate post lighting
- Security lights
Generator house: $1,000-2,000
- Enclosed, ventilated structure
- Away from main house (noise)
- Fuel storage area
Borehole & overhead tank: $3,000-5,000
- Borehole depth depends on water table (test first)
- Overhead tank: 2,000-3,000 liters minimum
- Pressure system for constant water flow
Month 17: Snagging & Corrections
Professional inspector ($500-800) identifies defects:
Common issues:
- Paint touch-ups needed
- Tiles cracked/uneven
- Doors/windows don't close properly
- Electrical sockets loose
- Plumbing leaks
- Cracks in walls
Contractor must fix ALL items before final payment.
Create punch list with photos. Nothing gets paid until everything is corrected.
Month 18: Final Inspection & Handover
You should be physically present for this (or trusted representative with legal authority).
Final walkthrough checklist:
✅ All rooms complete and clean
✅ All fixtures working
✅ No visible defects
✅ Doors/windows have keys
✅ Generator operational
✅ Water system working
✅ Electricity connected
✅ Final payments verified against work done
Documents you receive:
- As-built drawings (what was actually built)
- Equipment manuals
- Warranty documents
- Maintenance schedule
- Spare tiles, paint for future touch-ups
Final payment: Only after EVERYTHING is verified and complete.
Remote Monitoring: Tools & Systems
You're overseas. How do you actually monitor day-to-day?
Digital Monitoring System
1. CCTV cameras on site ($800-1,500 setup)
- 4-6 cameras covering key angles
- Internet-connected (4G router)
- Cloud storage or local recording
- You watch live from London/New York/Toronto
Benefits:
- See site activity 24/7
- Verify material deliveries
- Confirm contractor is actually working
- Deter theft
2. Project management software (Recommended: Trello, Asana, or Buildertrend)
Your PM updates daily:
- Tasks completed
- Photos attached
- Issues flagged
- Next day's plan
You review and approve payments from your phone.
3. WhatsApp Business
Create broadcast group:
- You
- Project Manager
- Quantity Surveyor
- Architect (for technical queries)
Rules:
- Daily photo updates (minimum)
- Weekly video walkthroughs
- Immediate notification of any issues
- Voice notes for complex explanations
4. Cloud-based budget tracker (Google Sheets or Excel Online)
Track every naira:
- Budgeted vs Actual costs
- Payment dates
- Outstanding amounts
- Receipts (photos uploaded)
Payment System That Prevents Fraud
NEVER send money directly to contractors or family.
System that works:
Your Bank (UK/US/Canada)
↓
Nigerian Bank Account (Your name only)
↓
Project Manager withdraws ONLY after:
- QS verifies work done
- Photos confirm completion
- You approve remotely
↓
Payment to contractors/suppliers
Payment schedule:
Foundation: 0% upfront, 100% on verified completion
Block work: 30% at lintel, 70% at wall completion
Roofing: 30% at truss, 70% at completion
Finishes: 30% start, 40% midpoint, 30% completion
Total upfront payment to contractor: ₦0. Not one naira.
They get paid for work DONE, not work PROMISED.
The 7 Deadly Mistakes (And How to Avoid Them)
Mistake #1: "My brother/cousin will manage it"
Why it fails:
- Family obligations trump your project
- They won't be strict with contractors (you're "family", should be flexible)
- Money accounting gets messy
- Relationship damaged when things go wrong
The fix: Professional PM from day one. Pay them. Keep family out of money decisions.
Mistake #2: Paying contractors upfront
Why it fails:
- They use your money on other projects
- No incentive to finish yours quickly
- When you complain, they disappear
The fix: Milestone payments only. Verified by QS. No exceptions.
Mistake #3: Not visiting at key stages
Why it fails:
- Critical mistakes happen that are expensive to fix later
- Contractor takes shortcuts you don't see in photos
- Your "specs" get ignored because you're not there to enforce
The fix: Visit minimum 3 times:
- After foundation (Month 5)
- After roofing (Month 9)
- Before final payment (Month 18)
Can't visit? Send someone with construction knowledge + legal authority to make decisions.
Mistake #4: Changing plans mid-build
Why it fails:
- Budget explodes
- Timeline extends indefinitely
- Structural issues from ad-hoc changes
The fix: Lock plans before foundation. Write "NO CHANGES" on contract.
Mistake #5: Choosing cheapest contractor
Why it fails:
- They won underbid (planned to cut corners)
- Use substandard materials
- Structural problems appear in 2-5 years
- Cost to fix exceeds savings
The fix: Choose mid-range quote from reputable contractor with verified past work.
Mistake #6: No contingency budget
Why it fails:
- Cement prices rise
- Steel costs increase
- Unexpected issues discovered
- Project stalls when money runs out
The fix: Add 20% contingency to EVERY budget line. Assume costs will increase.
Mistake #7: DIY project management
Why it fails:
- You're 6,000 miles away working full-time
- Can't respond to issues fast enough
- Don't know Nigerian construction standards
- Contractor exploits your distance
The fix: $8K-12K for professional PM is the best money you'll spend. They save you 10x that amount.
Real Numbers: What It Actually Costs
Here are real projects with real costs:
Case Study 1: Simple 3-Bedroom Bungalow
Owner: Tunde (London, IT Professional)
Location: Ibadan
Timeline: 14 months (planned 12)
Budget: $45,000 | Actual: $52,800 (17% over)
Breakdown:
- Construction: $38,000
- PM fees: $7,500
- Furnishing: $4,300
- Extras: $3,000
What went right:
- Professional PM from day one
- Visited 3 times during build
- No family involved in money
- Milestone payments only
Challenges:
- Cement price increase (added $3K)
- Plumber quit halfway (delayed 6 weeks)
- Had to redo electrical (contractor shortcuts)
Final result: Beautiful home, rental income ₦2.4M/year ($1,600/year), 8% ROI.
Case Study 2: 4-Bedroom Duplex
Owner: Angela (Houston, Nurse)
Location: Lekki, Lagos
Timeline: 20 months (planned 18)
Budget: $85,000 | Actual: $103,500 (22% over)
Breakdown:
- Construction: $72,000
- PM fees: $12,000
- High-end finishes: $14,500
- Generator/Solar: $9,000
- Fencing/Gate: $8,000
What went right:
- Architect supervised foundation
- QS verified all payments
- Premium materials specified and enforced
- CCTV installed from start
Challenges:
- Foundation issues (poor soil) = $8K extra
- "Governor's consent" delays (3 months)
- Kitchen cabinet supplier delayed (6 weeks)
Final result: Gorgeous home, worth $140K today (3 years later), 35% appreciation.
Case Study 3: 5-Bedroom Mansion (Caution Tale)
Owner: Chidi (Canada, Engineer)
Location: Abuja
Timeline: 36 months (planned 18)
Budget: $120,000 | Actual: $187,000 (56% over!)
What went wrong:
- Brother "managed" project (no formal PM)
- Paid contractor 50% upfront
- Changed plans 4 times mid-build
- Didn't visit for first 18 months
- No QS verification
Challenges:
- Contractor disappeared with $30K (after upfront payment)
- Had to hire new contractor mid-project
- Foundation had to be partially demolished and rebuilt
- Brother used $15K for "emergencies"
- Timeline doubled
Final result: House eventually completed. Beautiful. But cost $67K more than needed. Strained family relationships.
His advice: "Spend the $10K on professional PM. Would have saved me $70K and 2 years."
Your 12-Month Fast-Track Option
Standard timeline is 18 months. You can do it in 12 IF:
✅ You have all plans finalized BEFORE starting
✅ You hire experienced contractor (premium pricing)
✅ You have full budget available (no payment delays)
✅ You agree to premium material procurement (no waiting for cheapest supplier)
✅ PM is on site 6 days/week
✅ You visit 4 times instead of 3
Cost premium: +15-20% above standard timeline
When it makes sense:
- You're retiring/relocating soon
- Rental market is hot (start earning sooner)
- You can't manage 18-month oversight
When it doesn't:
- Budget is tight
- You want absolute lowest cost
- Market isn't urgent
The Decision Framework
Should you build from overseas or wait until you can oversee it yourself?
Build from overseas IF:
✅ You have $50K+ budget (minimum for proper oversight)
✅ You can visit Nigeria 2-3 times during build
✅ You're ready to hire professional PM ($8-12K)
✅ You need the house in next 2 years
✅ You have stable income for milestone payments
✅ You can monitor remotely (time zone allows checking daily updates)
Wait to build IF:
❌ Budget is under $50K (hard to afford proper oversight)
❌ You can't visit at all during 18 months
❌ You're unwilling to pay for PM (want family to manage)
❌ Your finances are unstable
❌ You can't handle stress of remote management
❌ You plan to move back to Nigeria within 2 years anyway
Alternative: Buy completed house instead of building. Less customization, but zero construction stress.
Your Action Plan (Start This Week)
Week 1: Planning
- Verify land ownership (if you have land)
- Decide on house size and budget
- Research architects in your chosen city
Week 2: Team Search
- Interview 3-5 architects (video calls)
- Request portfolios and fees
- Ask for PM referrals
- Join diaspora property groups for recommendations
Week 3-4: Design Start
- Select architect, sign contract
- Provide design requirements
- Review initial sketches
- Request 3D renderings
Month 2: Finalize Plans
- Approve final designs
- Get building permit
- Hire Quantity Surveyor
- Receive detailed budget
Month 3: Team Assembly
- Interview Project Managers
- Interview contractors
- Set up monitoring systems (CCTV, project software)
- Create payment schedules
- Transfer first payment tranche
Month 4: Break Ground
- Foundation starts
- Daily photo updates begin
- Site visit 1 (if possible)
Then follow 18-month timeline above.
The Bottom Line
Building a house in Nigeria from overseas is 100% doable. But it's NOT:
❌ Sending money to family and hoping for the best
❌ Choosing the cheapest contractor
❌ Managing it yourself from 6,000 miles away
❌ Skipping professional oversight "to save money"
It IS:
✅ Hiring professionals ($8-12K for PM is insurance, not expense)
✅ Paying only for verified work
✅ Visiting at key milestones
✅ Using technology for daily monitoring
✅ Budgeting realistic costs + 20%
✅ Accepting it costs slightly more to build remotely (but you get it done RIGHT)
Cost to build properly from overseas: $80K-120K for 4-bedroom house
Cost to build cheaply and fix mistakes: $120K-180K + stress + time
Your choice.
Hundreds of diaspora Nigerians build successfully from UK, US, Canada every year. They use this system. Their houses get finished. On budget (or close). On timeline (or close). No family drama. No contractor fraud.
You can too.
Ready to Build Your Nigerian Home from Overseas?
Holford Homes offers complete remote building management.
What we handle:
- ✅ Architect selection and design coordination
- ✅ Professional project management (daily oversight)
- ✅ Contractor vetting and management
- ✅ Quality surveyor verification
- ✅ Daily photo/weekly video reports
- ✅ Budget tracking and payment processing
- ✅ Remote monitoring setup
- ✅ Final inspection and handover
Our track record:
- 200+ overseas building projects completed
- Average timeline: 18 months (vs 36 months DIY)
- Average budget overrun: 12% (vs 40-60% DIY)
- Zero abandoned projects
Start Your Building Journey Today
📞 Book Free Consultation: Get personalized building plan →
🏗️ View Completed Projects: See our portfolio →
🧮 Estimate Your Cost: Use our calculator →
✅ Land Verification: Verify your land first →
💬 Questions about building from overseas?
Email: hello@holfordhomes.com | WhatsApp: +234 (0) 906 813 4175
Join 200+ diaspora Nigerians who built their dream homes from overseas using this exact system.
Your Nigerian home doesn't have to be a stress nightmare. It can be a smooth, professional process. 🏡
P.S. Scared of sending money to Nigeria? Our escrow service holds funds until work is verified and approved by you. Zero risk of contractor fraud. Zero risk of money disappearing. Book a consultation to learn how it works.

